Master Plan Design and Drawing
Ref. No:
Master Plan Design and Drawing
Project Summary | |||||
SN. | Particular | Amount | Result/ Deliverables | ||
1 | Site Survey with Surveyor & Assistant team with logistics of team (Site Field Visit & Inspection) | Surveyed Map (1:100 Scale) | |||
2 | Detailed Concept Planning of Building Block with Placement , Design and Development of Concept in Drawing (2D Autocad) for Real Construction Work by Concept Planner Expert team ( Construction Team , Engineer, Architect) | Master Plan Drawing with Beautiful Project placing all blocks in right position and land suitable design and structures with Engineering Safety and Space utilize focused | |||
3 | Detailed layout and plan of Septic Tank , Soak Pit ,Drain management | Drain and Water Filter Placement Layout, Plumbing, Soak Pit Layout Map | |||
4 | Master Plan Drawing & Design of Building block two story floor with plinth area 925 sq. ft. | Master Plan Including all Blocks in A1 Size Paper | |||
5 | Architectural Drawing of 3 Bedrooms, Kitchen Dinning ,4 toilets bathroom | Arch. Drawing with Elevation , top ,plan view in (A-2 Size) | |||
6 | Structural Column Plan , Layout , Truss Details , of Building Blocks | structural column plan , truss details ,section x-x of Each Block in (A-2 Size), Working Drawing of Building Blocks in A-2 | |||
7 | Foundation Footing Details & Working Drawing of Building Blocks | Footing Details and Working Drawing of Building in (A-2 ) Size Paper | |||
8 | Exterior Model of Building, Landscaping model & Exterior Visualization and Walk through of Complete project | During meeting discussion suggested not required. | |||
9 | Bill of Quantity Preparation For Building Blocks | BOQ with Cost For Construction &Material Specification of Structure, Roofing, Wall, Door/Window in details | |||
10 | Electrical & Lighting Placement Drawing | Light, Power Socket Drawing in A-2 Size | |||
|
Rs 80,000/- | ||||
COST ESTIMATE FOR Quality Assurance
COST ESTIMATE FOR Quality Assurance | |||||||
HIRING CONSULTING FIRMS TO CONDUCT FOR Quality Monitoring & Technical Reporting’s During Construction Work and Verifying Work Execution of Prefab Hostel Building with other Necessary Block Project. | |||||||
S.N | Description | Person | Unit Hr. | Rate | Total | Remark | |
A | Salary of Personnel | ||||||
2 | Architectural Engineer with Construction Supervision | 1 | 14 | 7500 | 105,000.00 | ||
3 | Civil Engineer with Supervision | 1 | 5 | 5500 | 27,500.00 | . | |
4 | Technical /Structure Engineer Supervision | 1 | 4 | 16500 | 66,000.00 | ||
Tank, Soak pit, Plumbing, Landscape Supervision | 1 | 5 | 3500 | 17,500.00 | |||
5 | Interior Design, Furniture, Kitchen Designer, Hall Design Consultant | 1 | 5 | 21500 | 107500.00 | ||
6 | , Electrical Engineer, Sanitary & Waste Manage Expert | 1 | 5 | 21500 | 107500.00 | ||
A | Sub Total | 431,000.00 | |||||
B | Miscellaneous expenses | ||||||
Communication cost | 7000.00 | ||||||
Drafting/ reports | 20000.00 | ||||||
Equipment’s, vehicles, computers, Software, Analysis | 20000.00 | ||||||
Sub Total | 47000.00 | ||||||
Grand Total | 478000.00 | ||||||
VAT @13% of G | 62140.00 | ||||||
Total (G+H) | 540,140.00 | ||||||
Building design process
Content
|
Building’s Construction process
Note: Final Costing and BOQ will be after Preparation of Detailed Project Report (Master Plan, Architectural Drawing , Structural Drawing , Opening Schedules, Foundation Details ) 1. Make Booklet Copy with All detailed drawings, master plan, photos.
|
Quality Assurance Process
1. Site Visit and Verify the construction work as per all detailed drawings, master plan, model and photos.
|
|
||||||||||
|
||||||||||
Project: Estimate cost of Hostel Building and Prefab Building Block at Dhading , Nepal | ||||||||||
Type of work: Construction of Prefab Building Block for Hostel with | ||||||||||
Complete works including Boundary wall | ||||||||||
Date: January 14 2020 | ||||||||||
S.n | Description of work | L, m | W,m | H,m |
Area (Sqm. /cum.) Total Price |
Deliverables | ||||
I | Construction of Prefab 6 Bedrooms for 35 Girls Each 20 Sqm.) | 1 | 15.700 | 7.65 | 2.75 | 120 | 4200071.85 | 6 Rooms with Door/Window, Light Non-Furnished ) | ||
II | Construction of Prefab Dinning Hall | 1 | 6 | 3.25 | 2.75 | 20 | 891735 | Hall Room Unfurnished | ||
III | Construction of Prefab Kitchen Hall | 1 | 6 | 3.25 | 2.75 | 20 | 723879 | Kitchen with modular Cabinets & Counter Top | ||
IV | Construction of Prefab Hall for Reading /TV/ | 1 | 10 | 4.00 | 2.75 | 40 | 1398800 | Hall Room with Unfurnished | ||
V | Construction of Prefab Meeting Hall | 1 | 8 | 3.25 | 2.75 | 26 | 965172 | Meeting Hall Unfurnished | ||
VI | Construction of Prefab Warden Family House | 1 | 12 | 4.00 | 2.75 | 48 | 1781856 | Family House with Non Furnished | ||
VII | Construction of Prefab Common toilet/bathrooms | 1 | 8 | 3.25 | 2.75 | 26 | 1077076 | Toilets with Commode, Tiles, Shower, tap | ||
VIII | Construction of Soak pit for Waste and Drain manage | 4 | 2 | 2.00 | 1.5 |
24 cu.m |
925000 | |||
IX | Construction of Water Tank | 1 | 4 | 2.00 | 2 | 12 cu.m | 1680000 | |||
Sub-total (A) |
NPR 13,643,589.85 | |||||||||
1.2 | Installation of Green Solar Plant for Energy Source 2 KW | 1 | 3.00 | 4.00 | NPR 725,300.00 | 2 Kw solar and 5 lights & System | ||||
1.3 | Futsal Playground of Size 40 feet x70 fet | 1 | 40.00 | 10.00 | NPR 925,320.00 | Futsal Playground | ||||
1.4 | Compound Work with Metal Pipe & CGI Fencing ( For 2 Ropani Land | 1 | 190 m | NPR 1,533,300.00 | Metal Fencing with CGI Sheet Cover | |||||
1.5 | Installation of Water Filter System | 1 |
NPR 455,500.00 |
Water Filter of 200 liter. | ||||||
1.6 | Installation of Pavement in Ground for 2 Ropani Land (Assumed) | 1 | 100 Sqm | NPR 1,150,000.00 | Hexagon Pavement in Ground | |||||
1.7 | Installation of Water Heating Solar for Hot Water Supply 200 l | NPR 325,000.00 | 200l water heating | |||||||
1.8 |
Installation of Solar System for Cooking 3 KW( Instead of Bio-Gas) |
1 | NPR 1,125,000.00 | Solar System for Cooking | ||||||
1.9 |
Sub-total(B) |
NPR 6,239,420.00 | ||||||||
Total(A+B) | NPR 19,883,009.00 | |||||||||
VAT 13% | NPR 2,584,791.28 | |||||||||
Scope of Work | Grand Total | NPR 22,467,801.13 | ||||||||
1 | Structure Metal , Prefab Wall , Doors/Window , Roofing False Ceiling ,Painting with turn-key solution | |||||||||
2 | 25-30 % Advance during MOU | |||||||||
3 | ||||||||||
Submitted by: |
Checked by: |
Approved by: | ||||||||
Project Timeline
Address: Dhading | ||||||||||||
Project : | ||||||||||||
Starting Date: March First Week | ||||||||||||
Completion Date: | ||||||||||||
Project Duration: 5 Months | ||||||||||||
S.N | Works | Duration (weeks) | Time Period (Week) | |||||||||
3-Mar | 25-Mar |
5 Apr. |
2 May |
20 May |
2-Jun | 25-Jun | 2-July |
3- Aug |
||||
1 | 30% | Design and Layout | 3 | |||||||||
2 | Site Visit and Custom Fabrication of structure for Project | 4 | ||||||||||
Material for structure and core part delivery | 2 | |||||||||||
3 | Structural Metal Frame Installation | 3 | ||||||||||
4 | 45% | Roof ,Flooring and Covering | 2 | |||||||||
5 | Gutter and Flooring PCC | 1 | ||||||||||
6 | Ceiling | 2 | ||||||||||
7 | Wall Panel installation | 3 | ||||||||||
8 | 25% | Wall Framing Window and Door | 2 | |||||||||
9 | Ground Pavement & Boundary | 3 | ||||||||||
10 | Electrification | 2 | ||||||||||
11 | Coloring | 2 | ||||||||||
Total Duration : Approx. 5 months including Building Works, Boundary Wall , Ground Pavement |
Materials Specification for Prefab
VERTICAL STRUCTURE MEMBERS |
GROUNG FLOOR Provide 8″x8″ primer coated C-Channel Coupled (box channel) as ISMC 150 column in ground floor11′ height connected to anchored nut bolt with foundation concrete base forming joint structure as per design & instruction of the Architect. |
FIRST FLOOR & PLINTH Provide 8″x8″ primer coated C-Channel Coupled (box channel) as column in first floor10′ height connected to truss at top and column from ground floor extended with foundation base forming joint structure as per design & instruction of the Architect. |
SECOND FLOOR Provide 8″x8″ primer coated C-Channel Coupled (box channel) as column in first floor10′ height connected to truss at top and column from ground floor extended with foundation base forming joint structure as per design & instruction of the Architect. |
HORIZONTAL STRUCTURE MEMBERS ( Beams & Frame) & Joist for First Floor and Half Second Floor |
Provide and install decking frame with I-beam channel of ISMB 8″ forming in I and II & a portion of III floors to complete structure of building for flooring that can withstand live load of 200 kg/sq. m. as per design & instruction of the Architect. |
CONCRETE BASE WITH TRENCHING – GROUND FLOOR |
Provide and lay Cement+ Concrete +Sand 1:2:4 (5’x5’x5’ ground excavation, digging and 5’x5’x5’ post foundation with 16 mm,12 mm road and Foundation anchored rod welded to footing rod to connect column all complete as per design. |
FLOORING WORKS |
BRICK SOLING Provide & lay one layer (110mm) brick soling with approved local chimney made first class brick in line and level including filling in the joints with sand all complete as per drawing, specification and instruction of Architect. |
PCC WORKS Provide PCC flooring with Cement, sand & aggregate of approved quality in 1:3:6 ratio including mixing, finishing, laying with proper compaction in perfect line, level & dimensions, curing all complete. |
DECKING WORKS ( I, II Floor) Provide and install in position Composite Metal Deck with Concrete PCC Flooring board for base flooring, in approved sample including filling gaps, etc. All complete as per the drawing and instruction of the Architect. |
WALL PARTITION / PANNELLING WORKS |
Prefab 75mm PARTITION WALL – INTERNAL AREA Provide and install in position full height VISAKA CEMENT board partition 3″ thick in G.I. metal frame, 8mm thick gypsum board on both side with glass wool in between, including all other hardware, expansion bolt, metal jambs where required, cutting opening for switch boards, etc. of approved sample including sealant, etc. All complete as per the drawing and instruction of the Architect. |
Prefab Panel 75mm BOARD PARTITION WALL – TOILET AREA Provide and install in position full height cement board partition 3″ thick in G.I. metal frame, 8mm thick cement board on both side with glass wool in between, including all other hardware, expansion bolt, metal jambs where required, cutting opening for switch boards, etc. of approved sample including sealant, etc. All complete as per the drawing and instruction of the Architect. |
GLASS PARTITION WITH ALUMINIUM FRAME Provide and install in position full height partition in approves aluminium section with 12mmclear toughened 12mm glass door beside & below fix with 12mm thick clear toughened glass and frosted sticker in approved aluminium frame, including all hardware, rubber gasket and sealant, etc. all complete as per the drawing and instruction of the Architect. |
CEMENT & PUFF PANEL PARTITION WALL -EXTERNAL AREA Provide and install in position full height cement board partition 4″ thick in G.I. metal frame, 18mm thick Brick & Stone finish puff panel on outer face and 8mm thich cement board on inner side with glass wool in between, including all other hardware, expansion bolt, metal jambs where required, cutting opening for switch boards, etc. of approved sample including sealant, etc. All complete as per the drawing and instruction of the Architect. |
Plain Cement Board on the Back Side of Building |
BRICK FINISH PUFF PANEL( Front, Left & Right Side View) |
STONE FINISH PUFF PANEL ( Left Side View) |
METAL WORKS |
STAIRCASE LANDING WITH METAL BASE Provide and install staircase with I- Beam supporting structure with metal angle and 18mm thick cement plank on landing all complete with material, installation, finishing and two coats of primer as per approved design in each floor as per the drawings. |
MS RAILING |
3″x3″ horizontal rails placed @6″ c/c |
4″x4″ VERTICAL POSTS placed @5′-1″ c/c |
ROOF TRUSS AND PURLINS |
MS WORKS FOR ROOF TRUSS & PURLINS Fabricate and install roof truss and perlins in MS black steel suqare or round section including welding, fixing, erection with all necessary hardware MS bed plates, shoes angles anchor bolts including two coat of primer painting all complete as per design and instruction of Architect. |
ROOFING SHEET Supply and lay colour coated 3mm UPVC sheets, weight 6.0kg/m2 of approved sample including overlapping, fixing/fasteners, GI-Hooks, sealing washers all complete as per specification and instruction of Architect. |
DOORS & WINDOWS |
UPVC DOOR UPVC frame door + UPVC cladding with hinges, lock, and fixing as per drawings all complete. |
ALUMINIUM FRAMED GLASS WINDOWS Aluminium alloy frame with glass: Double glazed window with fixing, hooks and installation as per drawings. Aluminium alloy frame 90 mm series complete material supply, slider, lock and installation. |
FALSE CEILING WORKS |
GYPSUM BOARD CEILING Provide and install 12 mm thick Gypsum Board (imported of the approved type) false ceiling, with G.I. Frame work of approved section, including all accessories, G.I. Hanging system with fiber tape on joints, cutting out of openings for all lights fixtures, linear grills and diffusers, G.I angle support on ends where ever required, all complete as per drawing. |
ACOUSTIC FALSE CEILING ( HALL) Provide and install 12 mm thick Accoustic false ceiling (imported of the approved type), with G.I. Frame work of approved section, including all accessories, G.I. Hanging system with fiber tape on joints, cutting out of openings for all lights fixtures, linear grills and diffusers, G.I angle support on ends where ever required, all complete as per drawing. |
PAINT WORK |
POP WORKS Provide and apply plaster of paris (POP) with Birla, Nerolac or equivalent quality Putty in approved texture with minimum two coats to internal plastered surfaces to make it smooth, filling the depression with putty and making it ready to receive paint, complete in all respect. |
PLASTIC EMULSION Provide and apply plastic emulsion paint (Nerolac Impression. Dulux. Asian or equivalent) of approved color and texture with minimum three coats of approved shade over a coat of primer to internal surfaces prepared smooth with carborandum, filling the depression with putty etc. complete in all respect. |
ENAMEL PAINT Provide and apply satin finish enamel paint (Nerolac Impression. Dulux. Asian or equivalent) of approved color with minimum three coats of approved shade over a coat of metal primer to the purlins, columns, beams and other surfaces as per design and instruction of the Architect. |
ELECTRICAL FITTINGS Complete with conduiting, wiring, installation of switching and power socket & termination in each floor 7W led lights 7 no.s and 7 power socket in each floor |
SANITATION ( Plumbing , Tiling & Fixture Works) |
SUPERVISION |